NPV v IRR:Question

Both of your NPVs are incorrect.

You need more decimal places on your IRRs: at least 2.

I used the NPV funcion incorrectly.

NPV of first NPV of second

($95,715.33) ($100,001.70) 7.7138

7.6840

NPV of first project is -95,715.33, IRR= 7.7138%

NPV of second project is -100,001.70, IRR= 7.6840%

Your NPVs are still wonky, but your IRRs are correct.

Excel’s NPV function is stupid: it assumes that the first cash flow occurs at time 1, not time 0. So you either have to omit the time 0 cash flow from the function (and add it outside the function), or you have to use all of the cash flows, then project the answer forward one time period (i.e., multiply by (1 + discount rate)).

Try it in your calculator, or do it long hand in Excel (i.e., don’t use the NPV function).

Graph will cross zero twice with non standard cash flows.

I took the following cash flows:

-100000 20350 40350 -20350 40350

and the following “cost of capital”:

2.0000 7.0000 9.0000 11.0000 21.0000

NPV=0 around 6.5%, 10.5%, 15.5%

IRR calculated by using IRR function in Excel in this case comes out to be negative

Whew! It took me close to an hour to do this. I need to learn how to use Excel after L1 ends :confused:

I did exactly that after I googled. I used the cash flow (at time t=0) outside the formula for NPV. I was using the wrong cost of capital. The answers calculated were for a cost of capital of 2%.

For 7%, NPV of first project = (95,715.33)

NPV of second project = (96,776.18)

If Excel thinks that the first cash flow starts at t=1, shouldn’t I be discounting back my answer by (1+discn rate) instead of multiplying?

Your numbers don’t look reasonable. Think of it this way: at a discount rate of 0% the first project will have an NPV of $20,000 (just add up the numbers). You have an outflow of $100,000 and inflows of $120,000; you cannot get an NPV of -$96,000.

No. It’s discounting the first cash flow (-$100,000) for one year, when it should be discounting it for zero years; you have to undiscount it one year (i.e., multiply by (1 + discount rate)) to get it back to where it belongs.

I entered the rates in the wrong format. The first project’s NPV is 1616.34 and the second project’s NPV is 1656.43. This means that the calculations for the second excel exercise that you gave are wrong too. Phew! I’ll save that for another time.

Yeah! I did miss that. Anyways, thanks a lot :slight_smile: And thank you for being back. You are a life saver.

Yes. I get the drift on the importance of NPV now.

Seems I am late… but everything seems good… as you have understood…

Thank you Exotichedge :slight_smile: