Wrong Statement in R32 - Capital Budgeting?

On Page 61:

https://gyazo.com/6223310c64677a7a91a62ef9546ea921

“Project B has the higher NPV below the crossover point, and Project A has the higher NPV above it.”

Should be the opposite right? Like:

“Project B has the higher NPV above the crossover point, and Project A has the higher NPV below it”

Anyone agree?

the original statement seems fine with me. Project B - shown in the dashed line, has higher NPV below the crossover point of 15.09 percent.

Oh my bad I interpreted the Discount Rate a wrong way (the opposite)